2012 Work Plans:
Repairs and Maintenance update:
- Concrete inspections will be taking place again this year. We should be rounding the corner on the concrete repairs.
- Driveways will be re-inpected and repairs and sealing will take place this summer.
- Bids are being accepted for unit painting (3 year phase).
- Roof & siding replacement. We are currently discussing options and taking bids. Both projects are going to be costly; therefore phased in over years.
Painting Phases:
- Phase I (2012): Inner Circle on Grandview Court.
- Phase II (2013): Outer Circle on Grandview Court.
- Phase III (2014): All of Liam and Westwood.
The date variation depends on what the inspections find.